ASPA – Rail Ferry

Initial Site Clearing – Over 500 Untreated Heart Pine & Cypress Timber Piles and Over 100 Raymond Pile were Removed Intermodal Railroad Relocation Geometry C hanges to ASD Boulevard Storm Water Management Construction of Elevated Railroad Deck & Ramps as well as the On Grade Rails & Bridges

ASPA-Mobile Refrigerated Services-Pier A South Warehouse Renovation

Rob’t J. Baggett worked directly for the Construction Managers, Bohnert Construction, to convert the existing Pier A South Warehouse to a reefer warehouse with blast freezers.  Our responsibilities included selective demolition, structural repairs, new insulated concrete slabs on grade, site work with site utilities and construction of two-story office complex located inside the warehouse. Key […]

City of Fairhope-Installation of SIGNA UV at Treatment Facility

In this project we replaced the existing Trojan UV 4000 disinfection system with the Trojan UV Signa disinfection system.  This work consisted of saw cutting, concrete demo and new concrete, removing the old disinfection equipment and installing the new equipment, all electrical and SCADA work.

AUSTAL – North Shipyard Expansion – Bay 3 & 4

Contracts were executed with Thompson Engineering in late December 2004 with construction beginning immediately to build a 106,660 SF aluminum fabrication and launch facility.  The facility includes a ridge frame metal building consisting of two main fabrication bays with a mezzanine between the bays and a 504 LF sheet pile/relieving platform bulkhead system Rob’t J. […]

Kimberly Clark Training Center

Pre-engineered metal building approximately 12,000 sf Interior custom designed by owner Construction began November 2018 and received certificate of occupancy July 2019

AUSTAL – Bay 5 Assembly Building

Bay 5 Production Shed   59,075 sf with 118’ eave height Approximately 25,000 lf of auger cast piling Building foundations & slab Erection of building which included an extensive mezzanine system, restrooms and offices Erection of two 50 metric ton overhead cranes All required utilities and drainage All required electrical installation Installation of 125’ bi-fold […]

Mobile Airport Authority – Main Gate, Logistics Center & Transshipment Hangar

MOBILE AIRPORT AUTHORITY – AIRBUS – PACKAGE C – MAIN GATE, LOGISTICS CENTER AT BROOKLEY COMPLEX & TRANSSHIPMENT HANGAR – 2015 MAIN GATE Office Building (approximately 3,200 sf) Unique sloped canopy roofing Construction began May 2014 – substantial completion January 2015 LOGISTICS CENTER AT BROOKLEY COMPLEX Retrofit warehouse area approximately 48,000 sf New office area […]